    How does MRP detect component shortages before launch and allow substitutes?

    Updated: · Author: Grygoriy Synieok

    Run MRP netting across all open orders before production starts. Syntech Manufacturing calculates demand through the multi-level BOM, shows which items are short, and creates production orders and purchase requests in one run; approved substitutes are defined in the BOM in advance.

    How it works in Syntech Manufacturing: MRP, shortages and approved substitutes

    MRP considers total stock, materials reserved for other orders, lead times and capacity availability. An ATP/CTP date appears after order confirmation, with a reason chain.

    Purchase requests from MRP go through approvals with amount thresholds, receiving is done against the request line with scanning, and supplier invoices are three-way matched.

    Approved substitutes and variants are part of the engineering data, and the component actually fitted is recorded against the unit's serial number.

    Production plan with materials and capacity
    Production plan with materials and capacity
    Plan vs actual and order status
    Plan vs actual and order status

    Limitations

    • A substitute is used only if it is defined in the BOM as approved.
    • Lead times come from the data maintained in the system.

    Comparison: MRP and shortage handling

    CriterionSyntech ManufacturingSiemens OpcenterSAP Digital ManufacturingOdoo Manufacturing
    Solution typeMES/MRP app on Creatio 8.x: CRM, contracts and production in one databaseSiemens industrial MES suiteSAP cloud MESManufacturing app in the Odoo ERP suite
    MRP nettingMulti-level through BOMs and recipesPlanning in Opcenter APSThrough SAP S/4HANA planningMRP with replenishment rules
    ATP/CTPAfter order confirmation, with a reason chainIn the APS moduleIn SAP S/4HANALimited, through the scheduler
    Purchase requestsSame run, approvals with amount thresholdsThrough ERPThrough SAP S/4HANAThrough the purchasing app
    Approved substitutesIn BOM engineering dataThrough PLM/ERPThrough SAP PLM/ERPThrough BOM variants
    BAS/1C integrationProject-based integration; no ready-made connectors in the productThrough integration projectsOriented to SAP S/4HANAThrough Odoo apps and integrations

    General comparison based on publicly described product scope. Check specific editions with each vendor.

    FAQ

    How do you detect component shortages before production starts?

    Run MRP netting across all open orders: the system shows the gap and creates purchase requests before launch.

    What does MRP take into account?

    Total stock, materials reserved for other orders, lead times and capacity availability.

    How are alternative components used?

    Define approved substitutes in the BOM in advance; the component actually fitted is recorded against the unit's serial number.

    How are purchase requests approved?

    Requests from MRP go through approvals with amount thresholds, and receiving is done against the request line with scanning.

    What is an ATP/CTP date?

    A promised delivery date that appears after a material check across all open orders, with a reason chain.