From order to shipment in one MES system
Live demo of SYNTECH Manufacturing: procurement, warehouse, MRP, production, payment, and shipment in one digital process
Key steps
This demonstration follows order ORD-36 for 100 SHR-600 IP54 distribution cabinets in Syntech Manufacturing, a MES solution based on Creatio. Follow the sequence from material verification through procurement, warehouse receipt, payment, production, and shipment to see how the demonstrated order progresses within one system.
1. Check the order and identify material shortages
- Open the customer order. Begin with the order for 100 distribution cabinets, as the manager does in the demonstration. This order provides the starting point for checking material availability and later creating the production plan, before shipping the finished cabinets directly from it.
- Check materials across every bill-of-materials level. Use the one-click material check shown in the video to verify the requirements against the bill of materials at all levels. This establishes which materials are available and which shortages must be addressed before the demonstrated production sequence proceeds.
- Review the missing items. In this example, the check identifies three missing items, including sheet metal for the welded enclosure. Review those shortages as the basis for procurement rather than treating the order as fully supplied; the next stage creates requests specifically for the missing materials.
- Note the initial promised date. The system immediately calculates September 30 as the promised date in the demonstration. Keep this initial result in view when following the example, because the later receipt of materials triggers another calculation and the subsequent check shows a different date.
2. Create and approve procurement requests
- Generate requests for the shortages. The system automatically creates procurement requests for the missing materials identified by the check. This carries the shortage information into the purchasing stage, connecting the material requirements of the cabinet order with the requests used to obtain the missing stock.
- Keep requests separate by supplier. Follow the demonstrated supplier-specific grouping rather than combining all shortages into a single request. The system creates a separate request for each supplier and takes account of minimum order quantities and order multiples when forming the procurement requests.
- Send the request for approval. Submit the procurement request for approval, as shown in the video, and have the supervisor approve it in the approvals section. This is the demonstrated approval step between creating the request and the procurement specialist marking it as ordered.
- Mark the approved request as ordered. The procurement specialist records this status after the supervisor's approval. The request then remains part of the demonstrated workflow: the warehouse operator receives goods against it, and the supplier invoice is subsequently created from it.
3. Receive materials and recheck availability
- Receive the goods against the procurement request. Use the request when recording the warehouse receipt, following the warehouse operator's action in the demonstration. The batch, incoming inspection, and label are created in one action, bringing these receipt-related records into the same stage of the process.
- Place and scan the received stock. Put the goods in a storage bin alongside the existing stock, as shown in the example. The warehouse operator scans both the bin and the batch, and stock balances update immediately to reflect the warehouse action.
- Follow the automatic MRP recalculation. Once the goods arrive, the system recalculates MRP automatically and sends a notification that the shortages have been resolved. This connects the warehouse receipt to the material-planning result, rather than leaving the original shortage check as the last availability assessment.
- Repeat the material check. In the demonstration, the repeated check confirms that all materials are now available. It also shows the promised date moving from September 30 to September 27; these are the results of this particular example, not a separate production or delivery guarantee.
4. Reconcile the supplier invoice and record payment
- Create the supplier invoice from the request. Continue from the procurement request rather than treating the invoice as an unrelated part of the example. The video shows the supplier invoice being created from that request, preserving the connection between purchasing and the subsequent invoice check.
- Use the automatic invoice comparison. The system checks the invoice against both the procurement request and the actual receipt. This brings the requested and received goods into the invoice-checking step before the demonstrated sequence moves on to approval and payment registration.
- Follow the approval-before-payment sequence. The transcript places approval before the accountant records payment. Keep that order when following the demonstration: invoice creation and automatic checking come first, followed by approval and then the accountant's payment-registration action.
- Record payment and observe the invoice status. After approval, the accountant registers the payment, and the invoice becomes paid. This completes the payment portion of the demonstrated sequence before the video turns to creating the production plan from the customer order.
5. Plan production and ship the finished cabinets
- Create the production plan from the order. Use the one-click action demonstrated in the video to create the plan. MRP expands the bill of materials without duplicating materials already ordered, connecting production planning with the purchasing work completed earlier in the sequence.
- Generate production orders and reserve materials. The system creates production orders for both the enclosure and the cabinet and reserves materials. Follow both production orders in the example, because the demonstrated process includes the enclosure as well as the finished cabinet rather than only the final assembly.
- Record output after the operations are complete. At the output-recording stage shown in the video, materials and enclosures are automatically deducted from their storage bins. This connects the completed production operations with the stock deductions described in the demonstration.
- Ship the finished cabinets directly from the customer order. The system reserves the finished cabinets in the storage bin, and the warehouse operator issues them. This final action completes the demonstrated path from the original order through procurement, warehouse receipt, payment, and production to shipment in one system.
Transcript
An order for 100 cabinets, from checking materials to shipment to the customer in one system. The manager opens the order and checks materials against the bill of materials at all levels with one click. Three items are missing. One of them is sheet metal for the welded enclosure. The system immediately calculates the promised date: September 30.
For the shortages, the system automatically creates procurement requests, separately for each supplier, taking into account the minimum order quantity and order multiples. We send the request for approval. The supervisor approves it in the approvals section, and the procurement specialist marks it as ordered.
The warehouse operator receives the goods against the request. The batch, incoming inspection, and label are created in one action. The goods are placed in a storage bin alongside the existing stock. The warehouse operator scans the bin and the batch, and stock balances update immediately.
As soon as the goods arrive, the system automatically recalculates MRP and sends a notification: shortages resolved. Another check. All materials are available, and the promised date has moved to September 27.
The supplier invoice is created from the request and automatically checked against the request and the actual receipt. After approval, the accountant records the payment, and the invoice becomes paid.
We create a production plan from the order with one click. MRP expands the bill of materials and does not duplicate materials that have already been ordered. The system creates production orders for the enclosure and the cabinet and reserves materials. The operations are complete, and when production output is recorded, the materials, together with the enclosures, are automatically deducted from the storage bins.
We ship the finished cabinets directly from the order. The system reserves them in the storage bin, and the warehouse operator issues them. From order to shipment in one system. Request a demonstration of Syntech Manufacturing on our website.
Live demo of Syntech Manufacturing MES solution based on Creatio — an end-to-end production process using the example of order ORD-36 (100 distribution cabinets SHR-600 IP54).
What we show:
— material verification: the system immediately sees deficits and calculates the promised shipment date;
— automatic generation of procurement requests for deficits - separately for each supplier, considering the minimum batch;
— warehouse receipt: batch, incoming control, and label are created with one action;
— placement in a cell with scanning — balances are updated instantly;
— three-way reconciliation of the invoice (request / receipt / payment) and payment registration;
— MRP calculation and generation of production orders in one click;
— shipment of finished products to the client directly from the order.
Order → procurement → warehouse → payment → production → shipment — in one system.
Website
Related answers: Syntech Finance Center
- How do you approve payment requests and see what remains to be paid? →
- How can you see a cash gap before the account runs out of money? →
- How do you control budgets by item and cost center before money is spent? →